Simulation research on transient process of subway train pantograph-catenary offline
-
摘要:
弓网离线对地铁安全运行带来不利影响. 首先建立弓网离线牵引系统仿真模型,然后对不同时长的离线状况进行仿真,通过对离线期间牵引逆变电路的直流侧电压、IGBT电压以及电机转子电流的暂态过程进行分析,获取不同离线时长对列车牵引过程电气特性的差异化影响. 研究结果对牵引系统故障诊断和维修策略制定有较好的理论指导作用.
Abstract:The pantograph-catenary offline has many adverse effects on the safe operation of the subway. Firstly, the simulation model of pantograph-catenary offline traction system was established, and then the offline conditions of different durations were simulated. By analyzing the transient process of the DC side voltage, IGBT voltage and motor rotor current of the traction inverter circuit during the offline period, the differential effects of different offline time lengths on the electrical characteristics of the train traction process were obtained. The results have a good theoretical guiding role for the fault diagnosis of the traction system and the formulation of maintenance strategies.
-
Key words:
- subway train /
- traction system /
- pantograph-catenary offline /
- transient process /
- simulation modeling
-
表 1 模型中牵引电机参数
Table 1. Traction motor parameters in model
参数 额定功率/kW 额定电压/V 额定电流/A 额定转速/(r•min−1) 最高转速/(r•min−1) 额定频率/Hz 功率因数 电路连接形式 参数值 190 1050 132 1800 3642 60 0.85 Y 表 2 英飞凌FD800R33KF2C型IGBT参数
Table 2. Parameters of Infineon FD800R33KF2C IGBT
参数 参数值 最大集射极间电压VCE/V 3300 栅极电荷Qg /µC 42 反向传输电容Cres /nF 6 开通延迟时间tdon /µs 0.38 上升时间tr /µs 0.38 -
[1] 吴积钦. 受电弓和接触网系统[M]. 成都: 西南交通大学出版社, 2010. [2] 高国强. 高速列车运行状态暂态过电压机理与抑制方法的研究[D]. 成都: 西南交通大学, 2012. [3] 魏文斌, 张婷婷, 高国强, 等. 弓网电弧对牵引传动系统电气特性的影响[J] . 高电压技术,2018,44(5):1589 − 1597. [4] 张婷婷. 高速列车弓网电弧的特性及其对牵引传动系统的影响[D]. 成都: 西南交通大学, 2018. [5] 李宇星. 基于改进Mayr电弧模型的动车组车体过电压及其抑制方法研究[D]. 成都: 西南交通大学, 2020. [6] 宋小翠, 刘志刚, 黄可. 基于状态空间分析法的高铁牵引网弓网燃弧电磁暂态影响[J] . 电力自动化设备,2017,37(12):184 − 191. [7] 宋小翠. 计及多工况燃弧的高速铁路车网建模及电磁暂态研究[D]. 成都: 西南交通大学, 2018. [8] 施博辰, 赵争鸣, 蒋烨, 等. 功率开关器件多时间尺度瞬态模型(Ⅰ): 开关特性与瞬态建模[J] . 电工技术学报,2017,32(12):16 − 24.